
Timeline for New Chapel Construction Preparation
|
Action |
Time |
Notes |
| Fundraising | Ongoing | Construction begins when funds are in hand. |
| CUP Approval | February 2018 | DONE! Construction must start within 36 months |
| Contractor Selection | April 2018 | Watkins Landmark Construction has been selected. Request for Proposal (RFP) process |
| Design Development | May-July 2018 | Structure & Mechanicals. Freeze design |
| Cost Estimate | May-July 2018 | |
| SRF Funding Approval | On hold | |
| Construction Drawings | February-April 2019 | Requires significant fixed-fee contract with architect |
| Building Permit | May-August 2019 | Phase 1, duration 3 to 5 months |
| Construction start | Dependent on funding | Break ground! Storm water, grading & utilities |
New Chapel, Phase 1 New Chapel Master Plan A brief history of our New Chapel project Visualization to manifest our New Chapel