Timeline for New Chapel Construction Preparation

      Action

      Time

     Notes

Fundraising Ongoing Construction begins when funds are in hand.
CUP Approval February 2018 DONE! Construction must start within 36 months
     
Contractor Selection April 2018 Watkins Landmark Construction has been selected. Request for Proposal (RFP) process
Design Development May-July 2018 Structure & Mechanicals. Freeze design
Cost Estimate May-July 2018  
SRF Funding Approval On hold  
Construction Drawings February-April 2019 Requires significant fixed-fee contract with architect
Building Permit May-August 2019 Phase 1, duration 3 to 5 months
Construction start Dependent on funding Break ground! Storm water, grading & utilities
     