Timeline for New Chapel Construction Preparation




CUP Approval February 2018 DONE! Construction must start within 36 months
Fundraising, Phase 1 March-December 2018 Funding to be approved by SRF
Contractor Selection April 2018 Request for Proposal (RFP) process
Design Development March-May 2018 Structure & Mechanicals. ~ 30% of total fee
Estimating Cost May-June 2018 Materials, methods, and cost estimate
Funding Approval July-December 2018 SRF, Phase 1 (chapel and utilities)
Construction Drawings January-March 2019 Requires significant fixed-fee contract
Disruption Planning January-March 2019 Access, organization, communications
Building Permit April-June 2019 Phase 1 of 3, depending on funding
Construction start July 2019 Break ground! Storm water, grading & utilities
Chapel complete June 2020 Includes altar, furnishings, Phase 1 landscape