Timeline for New Chapel Construction Preparation

      Action

      Time

     Notes

CUP Hearing February 2018 City Planning Commission Reviews CUP
CUP Approval March 2018 Construction must start in 36 Mos.
Fund Raising, Phase 1 March-December 2018 Funding to be approved by SRF
Contractor Selection March-April 2018 Request for Proposal (RFP) process
Design Development March-May 2018 Structure & Mechanicals. ~ 30% of total fee
Estimating Cost May-June 2018 Materials, methods, and cost estimate
Funding Approval July-December 2018 SRF, Phase 1 (chapel and utilities)
Construction Drawings January-March 2019 Requires significant fixed-fee contract
Disruption Planning January-March 2019 Access, organization, communications
Building Permit April-June 2019 Phase 1 of 3, depending on funding
Construction start July 2019 Break ground! Storm water, grading & utilities
Chapel complete June 2020 Includes altar, furnishings, Phase 1 landscape